The buyer is requesting professional architectural and engineering services to install Level 3 electric vehicle chargers at four DTMB facilities in Michigan. The project includes a study phase, preliminary and final design, and construction administration. Services will involve electrical system modifications, site work, and architectural changes to accommodate the charger installations.
- 3/3/2025 - Pre-proposal meeting
- 3/12/2025 - Question deadline
- 3/20/2025 - Proposal Due Date
Refer to RFP
- Perform Phase 100 study to evaluate sites for EV charger installation
- Develop Phase 400 preliminary design for EV charger installations
- Create Phase 500 final design and contract documents
- Provide Phase 600 & 700 construction administration services
- Modify existing electrical systems and equipment as required
- Install new conduits and wiring for Level 3 chargers
- Make exterior site modifications, signage and pavement markings
- Perform architectural modifications to accommodate electrical work
- Submit design reviews at 50% and 90% completion
- Prepare cost estimates at 90% design completion