This RFP is currently open for proposals.
Sign up for an account to get RFPs matching your business in your inbox.

Level 3 Charger Installation at Various DTMB Parking Locations

3/20/2025
-
Michigan

Department Of Technology, Management And Budget

The buyer is requesting professional architectural and engineering services to install Level 3 electric vehicle chargers at four DTMB facilities in Michigan. The project includes a study phase, preliminary and final design, and construction administration. Services will involve electrical system modifications, site work, and architectural changes to accommodate the charger installations.

  • 3/3/2025 - Pre-proposal meeting
  • 3/12/2025 - Question deadline
  • 3/20/2025 - Proposal Due Date
Refer to RFP
  • Perform Phase 100 study to evaluate sites for EV charger installation
  • Develop Phase 400 preliminary design for EV charger installations
  • Create Phase 500 final design and contract documents
  • Provide Phase 600 & 700 construction administration services
  • Modify existing electrical systems and equipment as required
  • Install new conduits and wiring for Level 3 chargers
  • Make exterior site modifications, signage and pavement markings
  • Perform architectural modifications to accommodate electrical work
  • Submit design reviews at 50% and 90% completion
  • Prepare cost estimates at 90% design completion

Want to Save Time Drafting Proposals?

We generate a proposal draft so you don’t have to start from scratch. Learn more how you can save up to 80% of your time writing proposals.